EROOR가 자꾸 생겨서요,,,,,,
2006-03-21
아래같은 에라 메세지가 계속해서 생기는데,,,,,,,,,
그이유를 찾을수 없어서요,,,,,
답변부탁드립니다.
******** WARNING ! **********************
Calculation not converged in the calculation
The result is not guaranted to be reliable
Check data, change data and run again
Calculation not converged in STEP 15
Change data and run again
Calculation not converged in STEP 16
Change data and run again
Calculation not converged in STEP 17
Change data and run again
데이타파일은 다음과 같슴니다.
project 환기구 #4
soiL 1 매립층
7.500 1.800 0.900 0 28.8 1523 -1
2 풍화토
13.200 2.000 1.100 2 32 2712 -1
3 풍화암
23.500 2.100 1.200 10 30 3090 -1
4 연암
26.300 2.400 1.500 15 37 6500 -1
5 경암
50.000 2.600 1.700 40 42 10000
vwall 1 14.300 0.039836 0.000567 21000000 1.0 1
2 39.310 0.013480 0.000215 21000000 1.80 0.915
strut 1 0.9 0.01348 17.018 3 0
2 3.0 0.01348 17.018 3 5
3 5.5 0.01348 17.018 3 5
4 8.0 0.01348 17.018 3 5
5 10.6 0.01348 17.018 3 5
6 13.4 0.01348 17.018 3 5
7 16.2 0.01348 17.018 3 5
8 19.0 0.01348 17.018 3 5
9 22.1 0.01348 17.018 3 5
10 24.9 0.01348 17.018 3 5
11 26.9 0.01348 17.018 3 5
12 32.9 0.01348 17.018 3 5
anchor 1 28.9 0.0010134 15 4 1.800 0
2 30.9 0.0010134 15 4 1.800 0
3 34.9 0.0010134 15 4 1.800 0
4 36.9 0.0010134 15 4 1.800 0
division 0.2
output 1
*
step 1 excavation 1.500
output 1.0
surcharge 1.500
iteration 100 0.1
excavation 1.500
rankine 1.000 0.0 60
water pressure 9.200 0.000 13.200 2.800 37.810 0.000
step 2 strut 1 and excavati 3.500
const strut 1
excavation 3.500
step 3 strut 2 and excavati 6.000
const strut 2
excavation 6.000
step 4 strut 3 and excavati 8.500
const strut 3
excavation 8.500
step 5 strut 4 and excavati 11.100
const strut 4
excavation 11.100
step 6 strut 5 and excavati 13.900
const strut 5
excavation 13.900
step 7 strut 6 and excavati 16.700
const strut 6
excavation 16.700
step 8 strut 7 and excavati 19.500
const strut 7
excavation 19.500
step 9 strut 8 and excavati 22.600
const strut 8
excavation 22.600
step 10 strut 9 and excavati 25.400
const strut 9
excavation 25.400
step 11 strut 10 and excavati 27.400
const strut 10
excavation 27.400
step 12 strut 11 and excavati 29.400
const strut 11
excavation 29.400
step 13 anchor 1 and excavati 31.400
const anchor 1
excavation 31.400
step 14 anchor 2 and excavati 33.400
const anchor 2
excavation 33.400
step 15 strut 9 and excavati 25.400
const strut 12
excavation 35.400
step 16 anchor 3 and excavati 37.400
const anchor 3
excavation 37.400
step 17 anchor 4 and excavati 37.810
const anchor 4
excavation 37.810
insertion check
ground settlement
step 18 PECK CHECK
peck 0.650 0.2 0
END