수압적용에 대한 문의사항입니다.. 2006-03-23

바쁘시겠지만 아래 Data검토 부탁드립니다...

풍화암상단은 17.170m이고요 풍화암상단-2m(19.170m)까지 수압을 적용시키고
19.170m이하로는 수압이 없다고 보려고 하는데
STEP 9번까지는 water press를 적용하여 내려왔는데, STEP 10번부터 수압을 0으로 적용하려면 STEP 10~15번까지 어떻게 Input Data를 넣어야 하나요?




SOIL 1 매립층 (모래)
1.683 1.80 0.90 1.0 25.0 1500 -1
2 충적층 (모래)
7.683 1.80 0.90 0.0 29.0 1600 -1
3 충적층 (자갈)
20.183 2.20 1.30 0.0 36.0 2800 -1
4 풍화암층
21.683 2.40 1.50 5.0 32.0 5000 -1
5 연암층
23.183 2.50 1.60 15.0 35.0 8000
6 보통암층
50.000 2.60 1.70 50.0 37.0 8000

VWALL 1 34.508 0.01348 0.000215 2.1E7 1.50 0.915


STRUT 1 0.550 0.02355 11.5 2.0
2 2.005 0.01348 11.5 3.0 30
3 4.505 0.01348 11.5 3.0 30
4 6.905 0.01739 11.5 3.0 30
5 9.305 0.01739 11.5 3.0 30
6 11.705 0.01739 11.5 3.0 40
7 14.105 0.01739 11.5 3.0 40
8 16.505 0.01739 11.5 3.0 40
9 19.105 0.01739 11.5 3.0 40
10 21.705 0.01739 11.5 3.0 40

ANCHOR 1 24.405 0.00128480 0.0 2.0 1.5 0.0
2 26.405 0.00128480 0.0 2.0 1.5 0.0
3 28.405 0.00128480 0.0 2.0 1.5 0.0
4 30.405 0.00128480 0.0 2.0 1.5 0.0

SLAB 1 31.308 1.8 11.5
2 23.808 0.5 11.5
3 17.308 1.5 11.5

WALL 1 30.758 33.008 1.5
2 27.758 30.758 1.5
3 23.808 27.758 1.5
4 20.808 23.808 1.5
5 17.308 20.808 1.5

DIVISION 0.2
OUTPUT 1

STEP 1 EXCAVATION TO 1.90
OUTPUT 0 0 0 0
ITERATION 20 0.1
RANKINE 1.0 0 33.33
SURCHARGE 1.0
EXCAVATION 1.90

STEP 2 CONSTRUCTION STRUT 1 AND EXCAVATION TO 2.505
CONSTRUCTION STRUT 1
EXCAVATION 2.505

STEP 3 CONSTRUCTION STRUT 2 AND EXCAVATION TO 5.005
CONSTRUCTION STRUT 2
EXCAVATION 5.005
WATER 2.005 0.0 5.005 3.000 19.170 0.0

STEP 4 CONSTRUCTION STRUT 3 AND EXCAVATION TO 7.405
CONSTRUCTION STRUT 3
EXCAVATION 7.405
WATER 4.405 0.0 7.405 3.000 19.170 0.0

STEP 5 CONSTRUCTION STRUT 4 AND EXCAVATION TO 9.805
CONSTRUCTION STRUT 4
EXCAVATION 9.805
WATER 6.805 0.0 9.805 3.000 19.170 0.0

STEP 6 CONSTRUCTION STRUT 5 AND EXCAVATION TO 12.205
CONSTRUCTION STRUT 5
EXCAVATION 12.205
WATER 9.205 0.0 12.205 3.000 19.170 0.0

STEP 7 CONSTRUCTION STRUT 6 AND EXCAVATION TO 14.605
CONSTRUCTION STRUT 6
EXCAVATION 14.605
WATER 11.605 0.0 14.605 3.000 19.170 0.0

STEP 8 CONSTRUCTION STRUT 7 AND EXCAVATION TO 17.005
CONSTRUCTION STRUT 7
EXCAVATION 17.005
WATER 14.005 0.0 17.005 3.000 19.170 0.0

STEP 9 CONSTRUCTION STRUT 8 AND EXCAVATION TO 19.605
CONSTRUCTION STRUT 8
EXCAVATION 19.605
WATER 16.605 0.0 17.170 0.565 19.170 0.0

STEP 10 CONSTRUCTION STRUT 9 AND EXCAVATION TO 22.205
CONSTRUCTION STRUT 9
EXCAVATION 22.205
WATER

STEP 11 CONSTRUCTION STRUT 10 AND EXCAVATION TO 24.905
CONSTRUCTION STRUT 10
EXCAVATION 24.905
WATER

STEP 12 CONSTRUCTION ANCHOR 1 AND EXCAVATION TO 26.905
CONSTRUCTION ANCHOR 1
EXCAVATION 26.905
WATER

STEP 13 CONSTRUCTION ANCHOR 2 AND EXCAVATION TO 28.905
CONSTRUCTION ANCHOR 2
EXCAVATION 28.905
WATER

STEP 14 CONSTRUCTION ANCHOR 3 AND EXCAVATION TO 30.905
CONSTRUCTION ANCHOR 3
EXCAVATION 30.905
WATER

STEP 15 CONSTRUCTION ANCHOR 4 AND EXCAVATION TO 33.008
CONSTRUCTION ANCHOR 4
EXCAVATION 33.008
GROUND SETTLEMENT
INSERTION CHECK
WATER

STEP 16 PECK CHECK
PECK 0.65 0.00 0.488
WATER 1.000 0.0

STEP 17 CONST SLAB 1 WALL 1
RANKINE 1.0 0 33.33
CONST SLAB 1
CONST WALL 1
WATER

STEP 18 CONST WALL 2
CONST WALL 2
WATER

STEP 19 CONST SLAB 2 WALL 3
CONST WALL 3
CONST SLAB 2
WATER

STEP 20 REMOVE STRUT 10
CONST WALL 4
REMOVE STRUT 10
WATER

STEP 21 REMOVE STRUT 9
CONST WALL 5
CONST SLAB 3
REMOVE STRUT 9
WATER

END